Electrical commissioning

What Electrical Commissioning Is

Electrical commissioning is the structured process of verifying that an electrical installation is safe, compliant, correctly installed, and performing as intended before it is handed over for normal operation. For EV charging sites, commissioning proves that power distribution, protection devices, earthing, communications, and charger operation work correctly under real conditions.

Why Electrical Commissioning Matters for EV Charging

Charging infrastructure is a high-duty, public-facing electrical load. Commissioning helps:
– Prevent safety hazards (shock, fire, touch voltage issues)
– Reduce early-life failures and nuisance trips
– Confirm protection coordination (breakers, RCD/RCBO, SPD)
– Validate charger performance (power delivery, metering, session control)
– Provide documentation needed for warranties, permits, and acceptance
– Improve uptime by catching installation issues before go-live

What Commissioning Typically Includes

A proper commissioning scope usually covers:

Visual and Mechanical Checks

– Correct cable routing, glands, IP sealing, torqueing, labeling
– Enclosure integrity, clearances, ventilation, corrosion protection
– DB/switchgear build quality and circuit identification

Electrical Safety Tests

– Continuity of protective earth and bonding
– Insulation resistance tests on circuits
– Earth fault loop impedance (Zs) (where applicable)
– RCD/RCBO testing (trip times and currents)
– Polarity checks and phase rotation (3-phase sites)
– Verification of voltage drop and thermal considerations (as relevant)

Protection and Power Quality Checks

– Breaker rating and curve verification vs cable sizing
– SPD installation and coordination
– Verification of selectivity/discrimination (as designed)

Functional Testing (EV Charger Specific)

– Power-up, self-tests, and fault handling
– Start/stop charging with intended authentication method (RFID/app/whitelist)
– Verify charging current/power delivery (per phase for AC)
– Communication checks (OCPP connectivity, backend registration)
– Load management tests (site cap enforcement, throttling response)
– Metering verification (including compliance metering where required)
– Emergency stop / isolation behavior (if applicable)

Documentation and Handover

– As-built single-line diagrams and cable schedules
– Test certificates and commissioning report
– Photos, labels, serial numbers, firmware versions
– User training and O&M documentation (manuals, maintenance intervals)
– Acceptance criteria sign-off (customer and installer)

Commissioning for Depots and Multi-Charger Sites

Large sites require additional checks:
– Group load tests (many chargers simultaneously)
– Phase balancing verification (AC)
– DB feeder thermal checks and hotspot inspection (where feasible)
– Validation of priority logic and power allocation rules
– Network resiliency checks (connectivity coverage across the yard)

Common Pitfalls

– Commissioning only one charger and assuming the rest behave the same
– Skipping full load management testing under realistic simultaneity
– Poor earthing/bonding work causing intermittent faults later
– Connectivity not tested in real locations (underground/metal structures)
– Incomplete as-built documentation making future service and expansion painful
– No clear acceptance criteria → disputes at handover

– Electrical panels / distribution boards
– Earthing system
– Earth fault loop impedance
– RCD/RCBO
– Insulation resistance test
– Dielectric withstand test
– Diagnostics